What is the general inspection checklist for Permanent Service?
  • Are all the requirements in the VRC for energizing service met? Requirements are: 
    • The service wiring and equipment, including the meter socket enclosure, shall be installed and the service wiring terminated. 
    • The grounding electrode system shall be installed and terminated. 
    • At least one receptacle outlet on a ground fault protected circuit shall be installed and the circuit wiring terminated. 
    • Service equipment covers shall be installed. 
    • The building roof covering shall be installed. 
    • Temporary electrical service equipment shall be suitable for wet locations unless the interior is dry and protected from the weather. 
  • Is the bond screw in place? 
  • If using aluminum service cables, has oxidant paste applied? 
  • If rebar is present in the footing/foundation, is it being used in the grounding electrode system (required)? 
  • If using ground rods, are there 2 and are they spaced at least 6ft apart? 
  • Is the required workspace around the panel present (36” minimum in front, 30” wide, 6ft above, and below to the floor)? 
  • If it is a sub-panel, are the grounds and neutrals separated and the bond screw removed? 

Show All Answers

1. Do I need an inspection?
2. Do I need to be present for every inspection?
3. What is the general inspection checklist for Erosion and Sediment Control (E&S)?
4. What is the general inspection checklist for Footings? (Can be inspected by a 3rd Party.)
5. What is the general inspection checklist for Foundations? (Can be inspected by a 3rd Party.)
6. What is the general inspection checklist for Groundworks? (Can be inspected by a 3rd party, but must be approved by the Building Official.)
7. What is the general inspection checklist for Slabs? (Can be inspected by a 3rd party.)
8. What is the general inspection checklist for Drain Tile/Waterproofing? (Can be inspected by a 3rd party.)
9. What is the general inspection checklist for Framing? (Framing and all Rough-In Inspections can be inspected at the same time.)
10. What is the general inspection checklist for Plumbing Rough-Ins?
11. What is the general inspection checklist for Electrical Rough-Ins?
12. What is the general inspection checklist for Mechanical Rough-Ins?
13. What is the general inspection checklist for Permanent Service?
14. What is the general inspection checklist for Insulation?
15. What is the general inspection checklist for Building Final?
16. What is the general inspection checklist for Deck Framing?
17. What is the general inspection checklist for Deck Final?